Hectoralos/GSOC 2020 work plan control

From Apertium
Revision as of 14:13, 7 June 2020 by Hectoralos (talk | contribs)
Jump to navigation Jump to search
Week Dates Goals Fulfilled
Bidix
(excluding
proper names)
Coverage WER Testvoc
---
Manual disamb. of frp texts
Frp monodix
(excl.
proper names)
Bidix
(excl.
proper names)
Non-WP
coverage
WP
coverage
WER Testvoc
(clean %)
---
Manual disamb.
(words)
1 1 June -
7 June
7,006 1,213
2 8 June -
14 June
~1,500
3 15 June -
21 June
~3,000
4 22 June -
28 June
~4,500
5 29 June -
5 July
~6,000 fra > frp >80%
frp > fra >85%
6 6 July -
12 July
~7,500
7 7 July -
19 July
~8,500
8 20 July -
26 July
~9,500 Disamb. of frp texts
9 27 July -
3 August
~10,500 fra-frp ~89%
frp > fra ~92%
fra-frp <25% Disamb. of frp texts
10 4 August -
10 August
~11,500
11 11 August -
17 August
~12,500 Testvoc: closed categories, vblex
12 18 August -
23 August
~12,750 Testvoc: adj, adv
13 24 August -
30 August
~13,000 fra > frp ~90.0%
frp > fra ~93.0%
fra > frp <20%
frp > fra <25%
Testvoc: n

See also

Work plan in the original proposal