Week | Dates | Goals | Fulfilled | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Bidix (excluding proper names) |
Coverage | WER | Testvoc - Manual disamb. of frp texts |
Frp monodix (excl. proper names) |
Bidix (excluding proper names) |
Non-WP coverage |
WP coverage |
WER | Testvoc (clean %) - Manual disamb. (words) | ||
1 | 1 June - 7 June |
7,006 | 1,213 | ||||||||
2 | 8 June - 14 June |
~1,500 | |||||||||
3 | 15 June - 21 June |
~3,000 | |||||||||
4 | 22 June - 28 June |
~4,500 | |||||||||
5 | 29 June - 5 July |
~6,000 | fra > frp >80% frp > fra >85% |
||||||||
6 | 6 July - 12 July |
~7,500 | |||||||||
7 | 7 July - 19 July |
~8,500 | |||||||||
8 | 20 July - 26 July |
~9,500 | Disamb. of frp texts | ||||||||
9 | 27 July - 3 August |
~10,500 | fra-frp ~89% frp > fra ~92% |
fra-frp <25% | Disamb. of frp texts | ||||||
10 | 4 August - 10 August |
~11,500 | |||||||||
11 | 11 August - 17 August |
~12,500 | Testvoc: closed categories, vblex | ||||||||
12 | 18 August - 23 August |
~12,750 | Testvoc: adj, adv | ||||||||
13 | 24 August - 30 August |
~13,000 | fra > frp ~90.0% frp > fra ~93.0% |
fra > frp <20% frp > fra <25% |