Week Dates Progress Evaluation
1 5/30 - 6/4 some data, test corpus
2 6/5 - 6/11
3 6/12 - 6/18
4 6/19 - 6/25
First evaluation 6/26 - 6/30 testing framework set up + prototype system in Python
5 6/26 - 7/2
6 7/3 - 7/9
7 7/10 - 7/16
8 7/17 - 7/23
Second evaluation 7/24 - 7/28 XML representation, finite-state implementation
9 7/24 - 7/30
10 7/31 - 8/6
11 8/7 - 8/13
12 8/14 - 8/20
13 8/21 - 8/27
Final evaluation 8/29 - 9/5 finite-state implementation in C++ with lttoolbox