User:Nikita Medyankin/Work plan
Schedule
Community Bonding Period (22th April—22th May)
- Getting to better know the workflow of how the rules are applied as I only worked with .t1x file while doing the coding challenge.
- Coming to know the core Apertium code.
- Producing the toy pair.
- Introducing ambiguity into chosen real language pairs.
Week 1 (23th—29th May)
Obtaining the weights by hand for toy pair.
Week 2 (30th May—5th June)
Obtaining the weights by hand for en-es. Experimenting on the process.
Week 3 (6th—12th June)
Implementation of deliverable (1).
Week 4 (13th—19th June)
Implementation of deliverable (1).
Testing and bug fixing.
Mid-term evaluation
Deliverable (1).
Week 5 (20th—26th June)
Start of implementation of deliverable (2).
Week 6 (27th June—3th July)
Implementation of deliverable (2).
Week 7 (4th—10th July)
Implementation of deliverable (2).
Week 8 (11th—17th July)
RBMT Summer School in Alacant: working on Apertium User-friendly lexical selection training (see Non-GSoC plans below).
Week 9 (18th—24th July)
RBMT Summer School in Alacant: working on Apertium User-friendly lexical selection training (see Non-GSoC plans below).
Week 10 (25th—31th July)
Implementation of deliverable (2).
Week 11 (1th—7th August)
Implementation of deliverable (2).
Testing and bug fixing.
Week 12 (8th—14th August)
Implementation of deliverable (2).
Testing and bug fixing.
Final week (15th—23th August)
Final testing and bug fixing.