Apertium-kaz-kir/Workplan
Jump to navigation
Jump to search
Contents
Major goals
- Good WER
- Clean testvoc
- 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
- Sort Adjective and Noun stems in kir.lexc into appropriate categories
- Trimmed coverage approaching 90%
Schedule
Timeline
See GSoC 2013 Timeline for complete timeline. Important coding dates follow:
- June 17th: coding begins
- July 29th - August 2nd: midterm evaluations
- September 16th - September 23rd: pencils down
- September 27th: final evaluation
Workplan
week | dates | goals | eval | accomplishments | notes |
---|---|---|---|---|---|
post-application period 3 - 24 May |
|
4/5 pass |
|
Demonstrated ability to add stems to dix and lexc. There are a couple easy lexical selection rules that could be written still. Needs to learn more about other aspects of apertium, including evaluation. —Firespeaker 06:45, 20 May 2013 (UTC) | |
community bonding period 27 May - 16 June |
|
||||
1 | 17 - 22 June |
|
|||
2 | 23 - 29 June |
|
|||
3 | 30 - 6 July |
|
|||
4 | 7 - 13 July |
|
|||
5 | 14 -20 July |
|
|||
6 | 21 - 27 July |
|
|||
7 | 28 - 3 August |
|
|||
midterm eval 2 August |
|
||||
8 | 4 - 10 August |
|
|||
9 | 11 - 17 August |
|
|||
10 | 18 - 24 August |
|
|||
11 | 25 - 31 August |
|
|||
12 | 1 - 7 September |
|
|||
13 | 8 - 15 September |
|
|||
pencils-down week final evaluation 16 - 23 September |
|