Apertium-kaz-kir/Workplan
< Apertium-kaz-kir
Jump to navigation
Jump to search
Revision as of 18:29, 19 May 2013 by Firespeaker (talk | contribs)
Contents
Major goals
- Good WER
- Clean testvoc
- 10'000 stems in bidix (~1000 stems per week, or ~200 per day)
- Sort Adjective and Noun stems in kir.lexc into appropriate categories
Schedule
Timeline
See GSoC 2013 Timeline for complete timeline. Important coding dates follow:
- June 17th: coding begins
- July 29th - August 2nd: midterm evaluations
- September 16th - September 23rd: pencils down
- September 27th: final evaluation
Workplan
week | dates | goals | eval | notes |
---|---|---|---|---|
post-application period 3 - 24 May |
|
|||
community bonding period 27 - 16 June |
||||
1 | 17 - 22 June |
|
||
2 | 23 - 29 June | |||
3 | 30 - 6 July | |||
4 | 7 - 13 July | |||
5 | 14 -20 July | |||
6 | 21 - 27 July | |||
7 | 28 - 3 August | |||
midterm eval 2 August | ||||
8 | 4 - 10 August | |||
9 | 11 - 17 August | |||
10 | 18 - 24 August | |||
11 | 25 - 31 August | |||
12 | 1 - 7 September | |||
13 | 8 - 14 September | |||
final evaluation |