Difference between revisions of "Apertium-kaz-kir/Workplan"

From Apertium
Jump to navigation Jump to search
(→‎Workplan: moar testvoc)
Line 2: Line 2:
* Good WER
* Good WER
* Clean testvoc
* Clean testvoc
* 10'000 stems in bidix (~1000 stems per week, or ~200 per day)
* 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
* Sort Adjective and Noun stems in kir.lexc into appropriate categories
* Sort Adjective and Noun stems in kir.lexc into appropriate categories
* Trimmed coverage approaching 90%


== Schedule ==
== Schedule ==

Revision as of 20:49, 19 May 2013

Major goals

  • Good WER
  • Clean testvoc
  • 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
  • Sort Adjective and Noun stems in kir.lexc into appropriate categories
  • Trimmed coverage approaching 90%

Schedule

Timeline

See GSoC 2013 Timeline for complete timeline. Important coding dates follow:

  • June 17th: coding begins
  • July 29th - August 2nd: midterm evaluations
  • September 16th - September 23rd: pencils down
  • September 27th: final evaluation

Workplan

week dates goals eval notes
post-application period
3 - 24 May
  1. finish coding challenge with WER ~10%
  2. trimmed coverage 45%
4/5 pass
  1. coding challenge WER ~12%
  2. trimmed coverage: 52%,48%
community bonding period
27 - 16 June
  1. run first testvoc
  2. write ≥4 lexical selection rules
  3. write ≥2 transfer rules
  4. write ≥3 disambig rules
1 17 - 22 June
  1. total 1500 stems in dix
  2. clean testvoc for <postadv> <ij>
  3. 500-word evaluation, WER ~10%
  4. trimmed coverage 51%
2 23 - 29 June
  1. total 2400 stems in dix
  2. clean testvoc for <num> <post>
  3. trimmed coverage 53%
3 30 - 6 July
  1. total 3200 stems in dix
  2. clean testvoc for <cnjcoo> <cnjadv> <cnjsub>
  3. trimmed coverage 55%
4 7 - 13 July
  1. total 4000 stems in dix
  2. clean testvoc for <adv>
  3. trimmed coverage 59%
5 14 -20 July
  1. total 4800 stems in dix
  2. clean testvoc for <prn> <det>
  3. trimmed coverage 63%
6 21 - 27 July
  1. total 5600 stems in dix
  2. trimmed coverage 68%
7 28 - 3 August
  1. total 6400 stems in dix
  2. trimmed coverage 70%
midterm eval
2 August
  1. total 6500 stems in dix
  2. 500-word evaluation, WER ~10%
  3. trimmed coverage 72%
8 4 - 10 August
  1. total 7200 stems in dix
  2. trimmed coverage 75%
9 11 - 17 August
  1. total 8000 stems in dix
  2. trimmed coverage 78%
10 18 - 24 August
  1. total 8800 stems in dix
  2. trimmed coverage 81%
11 25 - 31 August
  1. total 9600 stems in dix
  2. trimmed coverage 83%
12 1 - 7 September
  1. total 10400 stems in dix
  2. trimmed coverage 85%
13 8 - 15 September
  1. total 11200 stems in dix
  2. trimmed coverage 87%
pencils-down week
final evaluation
16 - 23 September
  1. total 12000 stems in dix
  2. 500-word evaluation, WER ~10%
  3. clean testvoc for all categories
  4. trimmed coverage 88%