Difference between revisions of "Apertium-kaz-kir/Workplan"
Jump to navigation
Jump to search
Firespeaker (talk | contribs) |
Firespeaker (talk | contribs) |
||
(17 intermediate revisions by the same user not shown) | |||
Line 185: | Line 185: | ||
# clean testvoc for {{tag|n}} {{tag|num}}{{tag|subst}} {{tag|np}} {{tag|adj}}{{tag|subst}} |
# clean testvoc for {{tag|n}} {{tag|num}}{{tag|subst}} {{tag|np}} {{tag|adj}}{{tag|subst}} |
||
# trimmed coverage 75% |
# trimmed coverage 75% |
||
|{{Workeval5|2}} |
|||
⚫ | |||
|rowspan="3"| |
|||
⚫ | |||
# stems in dix: 6493 |
|||
# trimmed coverage: 79.6%,74.1% |
|||
| |
| |
||
|- |
|- |
||
Line 194: | Line 196: | ||
# total 8000 stems in dix |
# total 8000 stems in dix |
||
# trimmed coverage 78% |
# trimmed coverage 78% |
||
|{{Workeval5|2}} |
|||
⚫ | |||
⚫ | |||
| |
| |
||
|- |
|- |
||
Line 203: | Line 204: | ||
# total 8800 stems in dix |
# total 8800 stems in dix |
||
# trimmed coverage 81% |
# trimmed coverage 81% |
||
|{{Workeval5|3}} |
|||
⚫ | |||
| |
|||
| |
| |
||
|- |
|- |
||
Line 213: | Line 213: | ||
# clean testvoc for {{tag|v}} |
# clean testvoc for {{tag|v}} |
||
# trimmed coverage 83% |
# trimmed coverage 83% |
||
|{{Workeval5|3}} |
|||
| |
| |
||
# stems in dix: 6730 |
|||
| |
|||
# trimmed coverage: 82.5%,78.4% |
|||
# azattyq_24455849 WER: 6.62% |
|||
| |
| |
||
|- |
|- |
||
Line 222: | Line 225: | ||
# total 10400 stems in dix |
# total 10400 stems in dix |
||
# trimmed coverage 85% |
# trimmed coverage 85% |
||
|{{Workeval5|3}} |
|||
| |
| |
||
# stems in dix: 7007 |
|||
# trimmed coverage: 84.2%,79.8% |
|||
| |
| |
||
* Good [[Turkic_lexicon#Kyrgyz|adjective typology]] |
|||
| |
|||
* Decent progress on coverage |
|||
* Not around much later in the week |
|||
* Still no testvoc... |
|||
—[[User:Firespeaker|Firespeaker]] 07:29, 10 September 2013 (UTC) |
|||
|- |
|- |
||
! 13 |
! 13 |
||
Line 231: | Line 241: | ||
# total 11200 stems in dix |
# total 11200 stems in dix |
||
# trimmed coverage 87% |
# trimmed coverage 87% |
||
|{{Workeval5|1}} |
|||
| |
| |
||
# stems in dix: 7454 |
|||
# trimmed coverage: 85.2%,80.4% |
|||
| |
| |
||
* Decent increase in coverage |
|||
| |
|||
* Still no testvoc |
|||
* Still ~600 unsorted ADJ |
|||
* Not around much |
|||
—[[User:Firespeaker|Firespeaker]] 20:06, 22 September 2013 (UTC) |
|||
|- |
|- |
||
!colspan="2" style="text-align: right"| pencils-down week<br />final evaluation<br />16 - 23 September |
!colspan="2" style="text-align: right"| pencils-down week<br />final evaluation<br />16 - 23 September |
||
Line 242: | Line 259: | ||
# trimmed coverage 88% |
# trimmed coverage 88% |
||
# release 0.1.0 and move to trunk |
# release 0.1.0 and move to trunk |
||
⚫ | |||
⚫ | |||
# stems in dix: 7546 |
|||
# trimmed coverage: 85.8%,81.6% |
|||
⚫ | |||
* Good coverage |
|||
* "Good" WER results |
|||
** But lots of # and * errors :( |
|||
* No work on testvoc |
|||
* Some ADJ sorted; still >500 unsorted |
|||
* only 2 sets of LRX rules since early in GSoC |
|||
* only 1 transfer rule since early in GSoC |
|||
⚫ | |||
!colspan="2" style="text-align: right"| Final evaluation |
|||
⚫ | |||
| |
| |
||
| |
| |
||
| |
| |
||
* Has improved coverage a certain amount |
|||
* Has not done anything else |
|||
* Mentors have had to nag to get him to work |
|||
* Has not been around enough |
|||
* Among the lowest-performing students |
|||
* Has not improved since midterm |
|||
* Last-ditch efforts not at all impressive |
|||
|} |
|} |
||
Latest revision as of 06:42, 23 September 2013
Contents
Major goals[edit]
- Good WER
- Clean testvoc
- 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
- Sort Adjective and Noun stems in kir.lexc into appropriate categories
- Trimmed coverage approaching 90%
Schedule[edit]
Timeline[edit]
See GSoC 2013 Timeline for complete timeline. Important coding dates follow:
- June 17th: coding begins
- July 29th - August 2nd: midterm evaluations
- September 16th - September 23rd: pencils down
- September 27th: final evaluation
Workplan[edit]
week | dates | goals | eval | accomplishments | notes |
---|---|---|---|---|---|
post-application period 3 - 24 May |
|
|
| ||
community bonding period 27 May - 16 June |
note: should be in IRC every day |
|
—Firespeaker 02:28, 2 July 2013 (UTC) | ||
1 | 17 - 22 June |
|
| ||
2 | 23 - 29 June |
|
|
| |
3 | 30 - 6 July |
|
|
—Firespeaker 20:43, 8 July 2013 (UTC) | |
4 | 7 - 13 July |
|
|
—Firespeaker 22:16, 22 July 2013 (UTC) | |
5 | 14 - 20 July |
|
|||
6 | 21 - 27 July |
|
|
—Firespeaker 18:21, 1 August 2013 (UTC) | |
7 | 28 - 3 August |
|
|||
midterm eval 2 August |
|
—Firespeaker 18:26, 1 August 2013 (UTC) | |||
8 | 4 - 10 August |
|
|
||
9 | 11 - 17 August |
|
|||
10 | 18 - 24 August |
|
|||
11 | 25 - 31 August |
|
|
||
12 | 1 - 7 September |
|
|
—Firespeaker 07:29, 10 September 2013 (UTC) | |
13 | 8 - 15 September |
|
|
—Firespeaker 20:06, 22 September 2013 (UTC) | |
pencils-down week final evaluation 16 - 23 September |
|
|
| ||
Final evaluation |
|
Tips and Tricks[edit]
Adding stems quickly[edit]
- Add top stems from frequency lists of unknown forms
- Use spectie's dix-entries-to-be-checked script