Difference between revisions of "Apertium-kaz-kir/Workplan"
Jump to navigation
Jump to search
Firespeaker (talk | contribs) |
Firespeaker (talk | contribs) |
||
Line 257: | Line 257: | ||
# stems in dix: 7546 |
# stems in dix: 7546 |
||
| |
| |
||
* Good WER results |
* "Good" WER results |
||
⚫ | |||
* Good coverage |
* Good coverage |
||
⚫ | |||
* No testvoc results |
* No testvoc results |
||
* Still close to 600 unsorted ADJ |
* Still close to 600 unsorted ADJ |
Revision as of 18:56, 22 September 2013
Contents
Major goals
- Good WER
- Clean testvoc
- 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
- Sort Adjective and Noun stems in kir.lexc into appropriate categories
- Trimmed coverage approaching 90%
Schedule
Timeline
See GSoC 2013 Timeline for complete timeline. Important coding dates follow:
- June 17th: coding begins
- July 29th - August 2nd: midterm evaluations
- September 16th - September 23rd: pencils down
- September 27th: final evaluation
Workplan
week | dates | goals | eval | accomplishments | notes |
---|---|---|---|---|---|
post-application period 3 - 24 May |
|
|
| ||
community bonding period 27 May - 16 June |
note: should be in IRC every day |
|
—Firespeaker 02:28, 2 July 2013 (UTC) | ||
1 | 17 - 22 June |
|
| ||
2 | 23 - 29 June |
|
|
| |
3 | 30 - 6 July |
|
|
—Firespeaker 20:43, 8 July 2013 (UTC) | |
4 | 7 - 13 July |
|
|
—Firespeaker 22:16, 22 July 2013 (UTC) | |
5 | 14 - 20 July |
|
|||
6 | 21 - 27 July |
|
|
—Firespeaker 18:21, 1 August 2013 (UTC) | |
7 | 28 - 3 August |
|
|||
midterm eval 2 August |
|
—Firespeaker 18:26, 1 August 2013 (UTC) | |||
8 | 4 - 10 August |
|
|
||
9 | 11 - 17 August |
|
|||
10 | 18 - 24 August |
|
|||
11 | 25 - 31 August |
|
|
||
12 | 1 - 7 September |
|
|
—Firespeaker 07:29, 10 September 2013 (UTC) | |
13 | 8 - 15 September |
|
|
||
pencils-down week final evaluation 16 - 23 September |
|
|
|
Tips and Tricks
Adding stems quickly
- Add top stems from frequency lists of unknown forms
- Use spectie's dix-entries-to-be-checked script