Difference between revisions of "Apertium-kaz-kir/Workplan"
Jump to navigation
Jump to search
Firespeaker (talk | contribs) m (→Workplan) |
Firespeaker (talk | contribs) |
||
Line 41: | Line 41: | ||
!colspan="2" style="text-align: right"|community bonding period<br />27 May - 16 June |
!colspan="2" style="text-align: right"|community bonding period<br />27 May - 16 June |
||
| |
| |
||
⚫ | |||
# run first testvoc |
# run first testvoc |
||
# run coverage scripts |
# run coverage scripts |
||
Line 48: | Line 47: | ||
# write ≥2 transfer rules |
# write ≥2 transfer rules |
||
# write ≥3 disambig rules |
# write ≥3 disambig rules |
||
⚫ | |||
| |
| |
||
| |
| |
||
# |
|||
# |
|||
# |
|||
# |
|||
# |
|||
# |
|||
| |
| |
||
|- |
|- |
Revision as of 07:39, 29 May 2013
Contents
Major goals
- Good WER
- Clean testvoc
- 12'000 stems in bidix (~1000 stems per week, or ~200 per day)
- Sort Adjective and Noun stems in kir.lexc into appropriate categories
- Trimmed coverage approaching 90%
Schedule
Timeline
See GSoC 2013 Timeline for complete timeline. Important coding dates follow:
- June 17th: coding begins
- July 29th - August 2nd: midterm evaluations
- September 16th - September 23rd: pencils down
- September 27th: final evaluation
Workplan
week | dates | goals | eval | accomplishments | notes |
---|---|---|---|---|---|
post-application period 3 - 24 May |
|
|
| ||
community bonding period 27 May - 16 June |
note: should be in IRC every day |
|
|||
1 | 17 - 22 June |
|
|||
2 | 23 - 29 June |
|
|||
3 | 30 - 6 July |
|
|||
4 | 7 - 13 July |
|
|||
5 | 14 -20 July |
|
|||
6 | 21 - 27 July |
|
|||
7 | 28 - 3 August |
|
|||
midterm eval 2 August |
|
||||
8 | 4 - 10 August |
|
|||
9 | 11 - 17 August |
|
|||
10 | 18 - 24 August |
|
|||
11 | 25 - 31 August |
|
|||
12 | 1 - 7 September |
|
|||
13 | 8 - 15 September |
|
|||
pencils-down week final evaluation 16 - 23 September |
|
Tips and Tricks
Adding stems quickly
- Add top stems from frequency lists of unknown forms
- Use spectie's dix-entries-to-be-checked script