Weekly plan[edit]

Week Dates Targe Testvoc Eval. (%) cov. raw (%) cov. trimmed (%) WER Bidix Err. Achieved ?
7 30 Gulan—5 Hezîran 80% 80.2 32.7 15,840 12,861
8 6 Hezîran—12 Hezîran 82% 80.2 34.6 15,841 12,832
9 13 Hezîran—19 Hezîran 83%
10 20 Hezîran—26 Hezîran 85%
11 27 Hezîran—3 Tîrmeh 85% n 500
12 4 Tîrmeh—10 Tîrmeh 86%
13 11 Tîrmeh—17 Tîrmeh 87% vblex
14 18 Tîrmeh—24 Tîrmeh 87%
13 25 Tîrmeh—31 Tîrmeh 88% adj
14 1 Ab—7 Ab 89%
15 8 Ab—14 Ab 90% 2000
16 15 Ab—21 Ab 90%
Week Dates Bidix Trimmed coverage Achieved Testvoc WER Achieved Notes
6 20/06—26/06 37% - 75% Midterm evaluation
7 27/06—03/07 42% <n> 65% Fix tags in BIDIX ( remove and replace Anusaaraka tags )
8 04/07—10/07 47% <np> <post> 55%
9 11/07—17/07 52% <adv> <adj> 45%
10 18/07—24/07 57% <vblex> -
11 25/07—31/07 62% - 30%
12 01/08—07/08 70% - 20%
13 08/08—14/08 80% all categories clean
14 15/08—21/08 90% Final evaluation. Tidying up, releasing