Line 12: Line 12:
 
|-
 
|-
 
| 3 || 01/07—07/07 ||
 
| 3 || 01/07—07/07 ||
  +
|-
  +
|colspan=3| '''Deliverable 1''':
 
|-
 
|-
 
| 4 || 08/07—14/07 ||
 
| 4 || 08/07—14/07 ||
Line 20: Line 22:
 
|-
 
|-
 
| 7 || 29/07—04/08 ||
 
| 7 || 29/07—04/08 ||
  +
|-
  +
|colspan=3| '''Deliverable 2''':
 
|-
 
|-
 
| 8 || 05/08—11/08 ||
 
| 8 || 05/08—11/08 ||
Line 28: Line 32:
 
|-
 
|-
 
| 11 || 26/08—01/09 ||
 
| 11 || 26/08—01/09 ||
  +
|-
  +
|colspan=3| '''Deliverable 3''':
 
|-
 
|-
 
| 12 || 02/09—08/09 ||
 
| 12 || 02/09—08/09 ||
Line 34: Line 40:
 
|-
 
|-
 
|}
 
|}
 
 
 
   
 
==Todo==
 
==Todo==

Revision as of 12:30, 3 June 2013

Plan de trabajo

Week Dates Tareas
0 21/05—16/06
1 17/06—23/06
2 24/06—30/06
3 01/07—07/07
Deliverable 1:
4 08/07—14/07
5 15/07—21/07
6 22/07—28/07
7 29/07—04/08
Deliverable 2:
8 05/08—11/08
9 12/08—18/08
10 19/08—25/08
11 26/08—01/09
Deliverable 3:
12 02/09—08/09
13 09/09—15/09

Todo

  • Set up a Makefile
  • Add an AUTHORS file -- r44881
  • Make loaders for the .ui files so people see them working.